Nathan Contractors
At Nathan Contractors, we value the ability of our team and their commitment to go above and beyond our clients’ expectations. Our people’s work ethic is second to none. They have the ability to take on every challenge, no matter how difficult, and succeed where most others fail.

1300 288 191

info@nathancs.com.au

6/7 Hudson Road

Albion, QLD 4010

19/41-43 Liardet Street

PO Box 3658, Weston, ACT 2611

Top

Author: Nathan Contractors

Moorabool Wind Farm Project Wrap Up, September 2019

After ten months on-site, we're saying goodbye to the Moorabool South Wind Farm in Victoria, having now completed our scope of works.  The Nathan crews worked through the blazing heat and freezing snow-like conditions to deliver this project on time and within budget. We're delighted to be wrapping up this project on a high, having broken all of our previous records for quantities of concrete poured and tower bases completed. Moorabool was one of three Wind Farm projects Nathan worked on in 2019, and we're glad to say we lived up...

Berrybank Wind Farm Project Update – August 2019

Nathan Contractor's fastest growing sector in 2018/19 has been energy infrastructure, with our third Wind Farm project commencing in July at Berrybank in Victoria.  MPC-Kinetic is busily constructing site roads and crane hard-stands, weather permitting - it's winter in Victoria, and hence the local conditions are very wet and challenging!  However, the project team is enthusiastically getting on with the job, and we expect to complete all concrete works around Xmas 2019. Nathan has continued to build a reputation for delivering outstanding structural concrete solutions on Wind Farm projects, safely and...

Sunshine Motorway Project Update April 2019

Nathan has been constructing bridges on the Sunshine Motorway upgrade project near Caloundra, QLD since mid-2018. The project is significant as it is Australia’s first Diamond Diverge interchange and we are excited to be part of the team that is at the forefront of Australian highway infrastructure: Image credit: Fulton Hogan Seymour Whyte Our Motorway crew was very busy in March lifting 58 precast-concrete beams into place over the Bruce Highway. This was no small task and it involved extensive night works and over 9,400 man-hours. The beams were installed safely, and on...

wind farm construction aus

Moorabool Wind Farm Project Update March 2019

Nathan started work at the Moorabool South wind farm project in late November 2018.  The project is located near Mount Wallace in Victoria and consists of 54 wind towers.  We are contracted to build the reinforced concrete tower bases and so far, have completed 27 bases. The guys on site have worked tirelessly through the heat, and the cold, and quickly bedded down their work methodologies to achieve record-breaking numbers: 5,000 m3 of concrete poured in February a record 4 bases poured in one week 27 bases poured to date and...

Sunshine Coast Motorway – Pouring of Pier Headstock

Since the landing of super-T’s in June 2018, Nathan has been busy making the finishing touches on four bridges and one culvert along the Sunshine Motorway. By Christmas this will bring us approximately 1/3 into the project. The latest bridges Nathan are constructing form part of Australia’s first divergent diamond interchange. These two structures involve over 1400m3 of concrete, 425 tonnes of steel, and are a unique solution to highway transitions. We are currently pouring headstocks on the central piers of both bridges, and you can see a short time-lapse of...

Sunshine Motorway, Caloundra QLD Underway

Nathan has commenced structural concrete works and formwork for the Sunshine Motorway project in Caloundra QLD. The project, consisting of over XYZkm of roadworks, will involve concrete placement, complex formwork, noise barrier construction and more. Due to the size and complexity of the project, completion is expected in late 2019. Stay tuned for more updates as work progresses....