Nathan Contractors
At Nathan Contractors, we value the ability of our team and their commitment to go above and beyond our clients’ expectations. Our people’s work ethic is second to none. They have the ability to take on every challenge, no matter how difficult, and succeed where most others fail.

1300 288 191

info@nathancs.com.au

6/7 Hudson Road

Albion, QLD 4010

19/41-43 Liardet Street

PO Box 3658, Weston, ACT 2611

Top

Sunshine Motorway Project Update April 2019

Sunshine Motorway Project Update April 2019

Nathan has been constructing bridges on the Sunshine Motorway upgrade project near Caloundra, QLD since mid-2018. The project is significant as it is Australia’s first Diamond Diverge interchange and we are excited to be part of the team that is at the forefront of Australian highway infrastructure:

highway construction aus

Image credit: Fulton Hogan Seymour Whyte

Our Motorway crew was very busy in March lifting 58 precast-concrete beams into place over the Bruce Highway. This was no small task and it involved extensive night works and over 9,400 man-hours. The beams were installed safely, and on time, continuing our track record of delivering quality results on schedule:

 

March – the numbers:

  • 58 – the number of beams installed
  • 43 – 63 tonnes – the mass range of precast beams
  • 9,400 – the number of man-hours involved in constructing the substructure to land the precast beams
  • 400 tonnes – the weight of the crawler crane used to land the beams over the Bruce Highway

Highlight Reel

We could tell you more about the placement of the beams, but why not show you instead?

A key part of the project has been the design and construction of a falsework system for the headstocks, seven metres above ground level:

 

 

Our crews not only successfully tackled the task head on but did so on-time and without incident, thanks to our three fearless leaders, Dannie Williamson, Andrew Pucket and Daniel Kelly. 

 

Dannie Williamson, Leading Hand

civil construction australia

 

Dannie led a team of six men to construct BR11 & 12 abutments, working tirelessly to deliver outstanding work and ensure the safety and well-being of his guys.

 

Andrew Pucket, Leading Hand 

civil construction aus

Andrew was responsible for overseeing a crew of eight men constructing pier headstocks, including the construction of a headstock in the centre median of the Bruce Highway. This required six weeks of continuous nightshift to complete and the crew went above and beyond to get the job done at the highest standard.

 

Daniel Kelly, Leading Hand 

civil construction australia

 

Daniel has been an integral part of the Nathan team, leading a crew of 3 men in the construction of bridge barriers on the project. To date he has lead his team to complete the installation of 98 precast parapet shells, casting 380 lineal metres of in situ concrete barrier over approximately 2,450 man hours. No small feat!

 

April Focus

We’re not ready to hang up our hard hats just yet. April will see us commencing construction of a new section of the motorway, which includes 1500m2 of bridge deck, 52 precast parapet panels and 200 lineal metres of in-situ concrete barrier.

 

Share